On 18 March 2026, Eni announced final investment decisions for two offshore developments in East Kalimantan: the South Hub, covering Gendalo and Gandang, and the North Hub, covering Geng North and Gehem. Eni said the projects are expected to start up in 2028 and reach a combined plateau of 2 billion cubic feet of gas and 90,000 barrels of condensate per day in 2029.
The development plan is designed to use existing infrastructure alongside a new floating production, storage and offloading vessel. The cited Eni announcement does not substantiate the USD 16 billion figure in this article’s headline. Eni announcement.
From the IBAI archive. Published 31 Mar 2026. This historical report reflects information available at the time.